Where units are actually being built
Bangladesh 2 units (Rooppur) · Japan 2 · Ukraine 2 · United Kingdom 2 (Hinkley Point C and Sizewell C) · Canada 1 · Hungary 1. Poland: first plant planned, 3 × AP1000, 2026 target (IYNG).
Nuclear Commons connects citizens, project developers, researchers, municipalities and capital around one transparent project record — from first dissemination through grants, demonstration, CAPEX, OPEX and revenue support.
Illustrative layout: pins are examples, not verified projects. The live layer is populated from sourced project records submitted by sponsors and reviewed before publication.
The real reactor situation, set against the opinion figures below. Counts come from the World Nuclear Association country profiles (reactor data based on IAEA/PRIS), retrieved 5 October 2026. Items marked IYNG are notes taken at the IYNG conference the same day: they are shown as conference notes and are not yet verified against a primary source.
Bangladesh 2 units (Rooppur) · Japan 2 · Ukraine 2 · United Kingdom 2 (Hinkley Point C and Sizewell C) · Canada 1 · Hungary 1. Poland: first plant planned, 3 × AP1000, 2026 target (IYNG).
WNA profiles record operating-lifetime extensions in Ukraine (15 in operation), United Kingdom, Sweden, Czechia, Finland, Hungary, Belgium, Switzerland and South Africa. IYNG: Sizewell B extended to 2055; Spain's government approved extended operation of a plant.
Kenya non-power applications, including schools · Rwanda nothing built yet, positioned as an African innovation hub (NEISA-Kigali) · Ukraine nuclear as the sole pillar of the grid · Italy law approved, construction reachable in 10 months (Ansaldo Nucleare) · Switzerland CERN and PSI research institutes · Hungary public outreach at Sziget festival · South Africa 5,200 MW expected.
How to read this: the three cards mix two evidence levels on purpose, and each item is labelled. Only numbers tagged WNA/IAEA are published as data; anything tagged IYNG stays a conference note until a primary source is attached. Sources for the machine-readable set: data/countries.json in the project repository.
A structured evidence layer for citizens and decision-makers. Compare technologies, costs, safety, waste, land, water, jobs and system impacts — with sources attached to claims.
What changes — and what doesn't — when reactor size, modularity and factory production change.
CAPEX, financing cost, construction duration, utilisation and market structure in one framework.
Separate scientific milestones from engineering readiness and future commercial deployment.
Every project is tagged to a technology family so funders, regulators and citizens compare like with like. Maturity labels are indicative; project rooms carry formal TRL evidence.
Proven gigawatt-scale units; the baseline for cost, schedule and licensing comparisons.
Factory-built modules (e.g. Rolls-Royce SMR, BWRX-300, NuScale) targeting repeatable build and lower unit capital.
Lead-cooled, sodium-cooled, molten-salt and high-temperature gas designs for higher temperature heat and new fuel cycles.
Very small units for remote sites, industry and defence-adjacent uses.
Magnetic and inertial confinement; public programmes (ITER, DEMO) plus private pilot-plant developers.
Medical and industrial radioisotopes, enrichment and fuel fabrication, spent-fuel and waste management, decommissioning.
Opinion is tracked as a set of indicators rather than one headline number, because support differs sharply by country, by site and by question wording.
Czechia is the highest in the EU; Austria shows the most negative views. Other member states lean positive over negative. Only these three values are shown because they are the ones verified; the full country table is the next data load.
Next to the opinion: the real fleet — World Nuclear Association, retrieved 05/10/2026. Czechia 6 reactors in operation, 0 under construction. Finland 5 in operation, 0 under construction. Poland 0 in operation, 0 under construction — first plant planned as 3 × AP1000 (IYNG note). Support figures alone do not build anything: the count is what shows how far a country has actually gone.
| Country | Measure | Value | Source |
|---|---|---|---|
| EU27 | Nuclear will have a positive effect on our way of life in the next 20 years | 56% positive · 35% negative | Special Eurobarometer 557, 2024 |
| Czechia | Expected positive impact of nuclear | 77% | Eurobarometer, autumn 2025 |
| Finland | Expected positive impact of nuclear | 71% | Eurobarometer, autumn 2025 |
| Poland | Expected positive impact of nuclear | 69% | Eurobarometer, autumn 2025 |
| Austria | Expected positive impact of nuclear | Most negative in the EU (no figure retrieved) | Eurobarometer, autumn 2025 |
| France | Nuclear is an asset for the country | 61% (6% liability) | Ipsos-BVA for Orano, 2026 (industry-commissioned) |
| Poland | Support the development of nuclear energy | 71% | Six-country survey after the 2022 energy crisis |
| Germany | Support the development of nuclear energy | 54% | Six-country survey after the 2022 energy crisis |
| Spain · Italy | Support the development of nuclear energy | 40% each | Six-country survey after the 2022 energy crisis |
Not a full 27-country table: the per-country figures from Special Eurobarometer 557 are published only in an interactive chart and in the underlying dataset, which are not yet loaded here. Rows use different questions and years, so compare within a row type, not across them. Country-level polls (Finnish Energy, DESNZ in the UK, Analysgruppen in Sweden) are also tracked by the World Nuclear Association.
Sources: Eurobarometer coverage (oEnergetice) · World Nuclear Association opinion tracker. The question measures expected impact, not direct support for building reactors.
| Country | In operation | Under construction | Shut down | Signals on the source page | Source |
|---|---|---|---|---|---|
| United States | 94 | 0 | 41 | life extension, SMR | WNA |
| France | 57 | 0 | 14 | SMR, non-power | WNA |
| Japan | 33 | 2 | 27 | life extension | WNA |
| Canada | 17 | 1 | 8 | life extension, SMR | WNA |
| Ukraine | 15 | 2 | 4 | life extension, SMR, non-power | WNA |
| United Kingdom | 9 | 2 | 36 | life extension, SMR | WNA |
| Sweden | 6 | 0 | 7 | life extension, SMR | WNA |
| Czechia | 6 | 0 | 0 | life extension, SMR, non-power | WNA |
| Finland | 5 | 0 | 0 | life extension, SMR | WNA |
| Hungary | 4 | 1 | 0 | life extension, SMR, non-power | WNA |
| Switzerland | 4 | 0 | 2 | life extension | WNA |
| South Africa | 2 | 0 | 0 | life extension, SMR, non-power | WNA |
| Mexico | 2 | 0 | 0 | life extension, SMR, non-power | WNA |
| Bulgaria | 2 | 0 | 4 | life extension, SMR | WNA |
| Belgium | 2 | 0 | 6 | life extension, SMR | WNA |
| Bangladesh | 0 | 2 | 0 | non-power | WNA |
| Poland | 0 | 0 | 0 | life extension, SMR | WNA |
| Italy | 0 | 0 | — | phase-out after the 1987 referendum | WNA |
| Australia | 0 | 0 | — | no nuclear power; uranium exporter | WNA |
Source: World Nuclear Association country profiles — reactor data based on IAEA/PRIS — retrieved 5 October 2026. Counts are power reactors only. "Signals" points to what else the source page records (life extensions, SMR programmes, non-power applications): pointers, not counts. Countries absent from the table (Russia, Spain, Austria, Colombia, Kenya, Rwanda) have no comparable count in that source: their information stays as labelled IYNG conference notes above until a primary source is attached. Reading note on Japan: the source counts 33 operable units while the IYNG note records 15 restarted, 3 permitted, 6 under review — the first is the licensed fleet, the second is what is actually generating.
A zero is information, not inactivity: Italy runs regulation, decommissioning and research; Australia is a major uranium producer. This table counts operating power reactors only.
Create a project identity once. Keep technical, financial, regulatory and community information together as the project matures. The three records below are illustrative examples, not live projects.
Industrial process heat and district heating concept.
Secure supply chain for medical isotope production.
Materials, manufacturing and qualification for fusion systems.
Real records are submitted by sponsors, sourced and reviewed before publication. Add your project →
The platform translates project maturity, geography, technology and financing need into a funding map — separating research grants from deployment finance and revenue support.
Starting with Europe. The platform separates research grants from state-aid-backed financing so a sponsor can see which is which. Status labels show whether a route is open, proposed or national.
| Instrument | Technology | Size | Status |
|---|---|---|---|
European Union | |||
| Euratom Research & Training 2026–27Research grants complementing Horizon Europe: fusion, safety, waste, materials, isotopes, skills. | Fusion · Fission · Isotopes · Waste | €330M (€222M fusion, €108M fission) | Open programme |
| InvestEU risk mitigation for SMRsProposed temporary top-up, delivered through the EIB. | SMR | +€200M through 2028 (proposed) | Proposed |
| Innovation FundProposed route for pre-commercialisation SMR projects; check each call’s scope. | SMR · Advanced | Call-dependent | Proposed / call-based |
| Scaleup Europe FundNamed in the EU SMR strategy as a route for innovative start-ups. | Start-ups | To be confirmed | Proposed |
| IPCEI on innovative nuclear technologiesPossible state-aid-approved multi-country project. | SMR · Advanced | To be confirmed | In development |
EU calls with deadlines (Euratom 2026–27) | |||
| Key enabling technologies for fusion power plantsFusion Energy Partnership. Opens 15 Sep 2026, closes 4 Mar 2027. Limited to entities in EU Member States, Ukraine and Switzerland. | Fusion | See call text | Open |
| European Nuclear Skills InitiativeHORIZON-EURATOM-2026-NRT-01-01. Opened 10 Mar 2026; closed mid-Sep 2026 (sources give 10 or 15 Sep). | Skills | See call text | Closed |
| OFFERR cascade fundingFast-track studies up to €50,000; complex projects up to €1M. | Fission | €50k – €1M | Check status |
Member states (financing and state aid, not grants) | |||
| Sweden — state aid for new nuclearState loans, two-way contract for difference and risk sharing; applications open since 1 Aug 2025; five applicants so far; EC approval required. | Large · SMR | Up to ~5 GW; SEK 220bn framework proposed over 12 years | Notified / negotiating |
| Czechia — Dukovany state aidState loan, power purchase agreement and stability guarantees; EC approved the mechanism for unit 5 on 30 April 2024. | Large | Unit-by-unit | Approved |
| France — EPR2 supportPlan to support six EPR2 reactors is under EC assessment. | Large | To be confirmed | Under assessment |
| Poland — first nuclear plant (PEJ)EC approved 10 Dec 2025 (SA.109707): equity of about 30%, state guarantees on all debt, 40-year two-way CfD. | Large | Investment PLN 178bn (€42bn); equity up to PLN 60.2bn | Approved |
| Netherlands — NEO NL and SMR programmeEC raised no objection in Feb 2026 to a €222M state loan for NEO NL. About €20M for private SMR licensability and feasibility studies; SMR financing consultation opened Apr 2026. | Large · SMR | €222M loan; ~€20M studies | Active |
| Italy — nuclear delegation lawSenate gave final approval on 23 Sep 2026; the government has 12 months to issue decrees. The law allocates no direct construction funding. | Large · SMR | None yet | Enabling law only |
| Finland — no dedicated grant foundFortum calculations suggest new plants may need state support. A private Google–Fortum contract for Loviisa has been reported. | Large · SMR | To be confirmed | Under discussion |
Europe now covers EU-level instruments plus Poland, Sweden, Czechia, France, the Netherlands, Italy and Finland. Still to add: Belgium, Romania, Slovakia, Slovenia, Bulgaria, Hungary, Spain and other EU calls. Deadlines in this table were taken from call listings and can shift; confirm on the EU Funding & Tenders portal. Sources: Euratom work programme · EU SMR strategy · Swedish Government · Poland (Enerdata) · Netherlands (WNA) · Italy (EUalive).
An indicator of venture and growth capital, set against the public instruments above. It shows direction and scale, not a single audited total.
| Notable private rounds | Amount | Date |
|---|---|---|
| Commonwealth Fusion SystemsFusion, US | $863M Series B2; $1bn round | Aug 2025; Jul 2026 |
| X-energyAdvanced SMR and fuel, US | $700M Series D; >$1bn IPO | Nov 2025; Apr 2026 |
| Proxima FusionFusion, Germany (Europe) | $518M | Jul 2026 |
| AntaresMicroreactors, US | $470M Series C | Jul 2026 |
| Helion EnergyFusion, US | $465M | Jun 2026 |
| Inertia EnterprisesFusion, US | $450M Series A | Feb 2026 |
| Blue EnergyModular nuclear plants, US | $380M Series B | Apr 2026 |
| Last EnergyMicroreactors, UK site in Wales | $100M Series C | Dec 2025 |
| Fortum → Steady EnergyDistrict-heating SMR, Finland (Europe) | Investment framework agreement | Feb 2026 |
Limits: no audited aggregate of private nuclear funding has been published since February 2022; the figures above come from different sources and definitions, so they must not be added together. They exclude utility and state-owned spending and project debt. The series covers 2024 to date. Most capital is US-based; European private rounds are far smaller. Sources: Axios via Yahoo Finance · Fusion Industry Association · S&P Global figures · Nasdaq Private Market · Last Energy.
Instead of rebuilding the story for every funder, maintain a living evidence base and generate the package required for each stage.
Create the project profile, funding brief and public evidence room in one workflow.
Two ways to take part. Submissions are reviewed manually — nothing appears on the map until the record is sourced.
Reviewed manually. Each published record carries at least one public source.
One email a month: new funding calls, opinion shifts and projects added. Unsubscribe anytime.
Prefer plain email? Write to vittorio.rossello@gmail.com.
Nuclear Commons is an independent project. It receives no funding from nuclear vendors, utilities or industry associations, and it carries no advertising. Where a source is industry-commissioned — for example the Orano-commissioned French poll — the row says so, because that affects how the number should be read.
Coverage today is uneven by design: EU instruments and seven member states are mapped, other member states and non-EU regions are still to be added. Country opinion data is partial. Private capital figures come from different providers with different definitions.
Nothing here is investment, legal or regulatory advice.